FREE TOOL · ELECTRICIANS
Apply BS 7671 diversity factors to your circuit schedule and calculate the after-diversity maximum demand — used to size consumer units, main switches, and incoming supplies.
ADMD
205.3 A
after diversity
kW equivalent
47.2 kW
at 230V single-phase
Supply upgrade required — contact DNO
After-diversity maximum demand of 205.3A exceeds the standard 100A single-phase domestic supply. Contact your DNO (Distribution Network Operator) to arrange a supply upgrade before commissioning. Lead times vary by network operator.
| Circuit | Rated (A) | Diversity | Demand (A) |
|---|---|---|---|
| Lighting circuit(×2) | 12 | 66% | 7.9 |
| Socket outlets (13A ring)(×8) | 256 | 100% (first 2) + 40% | 140.8 |
| Cooker / Hob (30A+)(×1) | 32 | 10A + 30% remainder | 16.6 |
| Electric shower(×1) | 40 | 100% | 40 |
| Total | 340 | 205.3 |
Next step
Turn these figures into a professional PDF quote or invoice — free, no account needed to start.
After-diversity maximum demand (ADMD) is calculated by applying BS 7671 diversity factors from Appendix 1 to each circuit type, then summing the derated loads. It is always lower than the raw connected load.
All lighting circuit loads are summed and multiplied by 0.66. A house with two 6A lighting circuits has a connected load of 12A, but after diversity: 12A × 0.66 = 7.9A demand. This reflects the reality that not every light in every room will be on simultaneously at maximum brightness.
The first two socket ring circuits are taken at 100% of their rated current. Additional rings get 40% diversity. Example: eight 32A rings = 2 × 32A (100%) + 6 × 32A × 0.4 = 64A + 76.8A = 140.8A connected, but 64A + 76.8A = 140.8A total... wait, the diversity applies: first two at 32A each = 64A; remaining six at 32A × 0.4 = 76.8A → total demand = 140.8A? No: first two = 2 × 32 = 64A; remaining six = 6 × 32 × 0.4 = 76.8A. Total = 140.8A. The 40% factor reduces the marginal impact of additional socket circuits substantially.
Per the IEE On-Site Guide Table A1: cooker demand = 10A + 30% of (rated current − 10A), plus 5A if a socket is in the cooker control unit (this calculator omits the socket addition for simplicity). A 32A cooker: demand = 10 + 0.3 × (32 − 10) = 10 + 6.6 = 16.6A. This reflects intermittent use — only some hob rings and the oven will be on simultaneously at full power.
PAS 1899 (Electric Vehicle Smart Charging) requires EV chargers to be assessed at 100% of rated current for maximum demand purposes, with no diversity. A 7kW charger on a 32A circuit contributes 32A to the ADMD with no reduction. This is the single biggest change to domestic ADMD calculations since EV adoption began — a single charger can add as much load as two socket ring circuits.
WORKED EXAMPLE
A 4-bed detached house with existing circuits wants to add a 7kW EV charger and a 3kW heat pump. The electrician calculates whether the existing 100A supply can accommodate the additions.
Existing ADMD (typical 4-bed)
~64A
EV charger (32A, 100%)
+32A
Heat pump (16A, 75%)
+12A
New ADMD
~108A
Assessment outcome
Contact DNO — 108A > 100A
Supply upgrade to 150A required · Or install 7kW load-balancing EV gateway to stay within 100A
This illustration uses typical diversity values. Always conduct a full site survey and refer to the current edition of BS 7671 and IEE On-Site Guide before advising customers.
Calculate household electricity consumption and consumer unit upgrade needs.
Check volt drop compliance across cable runs per BS 7671.
Select the correct cable size for current-carrying capacity and volt drop.
Calculate the right BTU and kW capacity for any room.
Calculate your income tax, NI and monthly set-aside for 2024/25.
Set your overhead recovery rate and target net margin.
Calculate true job cost including labour, materials, and overheads.
Solve for V, I, R, and P — enter any two values.
Convert between kW, kVA, and amps for single and three-phase.
Check BS 7671 45% fill rule for cable conduit runs.
Next step
Turn these figures into a professional PDF quote or invoice — free, no account needed to start.
Common questions about max demand, diversity factors, and supply upgrades.
Maximum demand (MD) is the highest electrical load a premises is likely to draw from the supply at any one time, expressed in amps or kilowatts. It is used to size the incoming supply, the main switch, the consumer unit, and the service cable from the distribution network. If the MD exceeds the rated capacity of the supply (typically 100A single-phase for domestic premises), the DNO must be consulted about a supply upgrade. Oversizing wastes money; undersizing causes tripping, overheating, or voltage sag.
Diversity is the statistical likelihood that not all circuits will be at full load simultaneously. BS 7671 Appendix 1 (formerly Table A1 in the On-Site Guide) defines diversity factors for common domestic circuit types. For example, socket outlet rings: 100% of the first 2 sockets, then 40% of the remainder. Lighting: 66% of the total installed load. Cookers: 10A + 30% of the remaining rated load (after the first 10A) + 5A if a socket is incorporated. These percentages acknowledge that, in practice, not every socket, light, and appliance is on full blast simultaneously.
A standard 100A single-phase domestic supply (100A × 230V = 23kW) is sufficient for most UK homes without electric heating. With typical BS 7671 diversity applied, a house with a 9kW shower, a 12kW cooker, standard socket ring circuits, and lighting usually comes out at 60–80A after diversity — comfortably within 100A. However, adding a 7kW EV charger (32A dedicated circuit, no diversity allowed under PAS 1899), a heat pump (16A), and an electric shower simultaneously can push toward or past 100A, warranting a supply upgrade or load management device.
Commercial premises do not benefit from the same domestic diversity factors. For small commercial units, electricians typically calculate the connected load (sum of all circuit ratings) and apply a demand factor based on the type of business — typically 60–80% for most commercial uses. For larger premises, a full load schedule is drawn up, showing circuit types, installed watts, and demand factors. The IEE Guidance Note 1 (Selection and Erection) and Electricians' Guide to the Building Regulations both provide worked commercial examples.
You need to contact the Distribution Network Operator (DNO — e.g. UK Power Networks, Western Power Distribution, SP Energy Networks) when the calculated maximum demand exceeds the existing cut-out fuse rating (usually 100A for domestic). The DNO will arrange for the supply fuse and sometimes the meter tails to be upgraded — typically to 150A or 200A for single-phase, or conversion to three-phase. Lead times vary from a few weeks to several months. The DNO upgrade is separate from the consumer unit work done by your electrician.
A 7kW (32A) EV charger draws its full rated current for 4–8 hours overnight — it cannot be reduced below its design current in the same way a heating circuit can. PAS 1899 (the EV charger installation standard) requires that EV chargers be assessed at 100% of their rated current for maximum demand purposes, with no diversity. This is why a single 7kW EV charger can push a previously comfortable home close to its 100A supply limit. Smart charge scheduling (time-locking to off-peak hours when other loads are low) or a load-balancing gateway device are common mitigations.
Maximum demand is the peak instantaneous draw from the supply, used to size protective devices and supplies. A load calculation (or energy audit) considers both peak demand and duration — used for tariff selection, battery storage sizing, and predicting energy costs. A property can have a low maximum demand but high energy consumption (e.g. underfloor heating running 16 hours/day at 4kW) or a high peak demand but low consumption (e.g. a 9kW shower running 10 minutes/day). Both calculations are needed for different design decisions.